Hendra

Case Study – Hendra Holiday Park

Hendra Holiday Park 

Total Annual Cost Benefit – £27,821

Total Cost Benefit (20 years) – £556,423

System Pay Back – 4.1 Years

THE CLIENT

Situated just minutes from Newquay’s golden sandy beaches the multi-award-winning Hendra Holiday Park, set in 80 acres of landscaped parkland truly has it all. Boasting a string of awards for its facilities, and accolades for its environmental and sustainable tourism achievements, Hendra offers holidays with a truly family ambiance. The park is the perfect choice for a family fun Cornwall holiday by the seaside and its central Cornwall location makes it the perfect spot for exploring the county.

THE CHALLENGE

Hendra Holiday Park is renowned for sustainable development and the owners wanted to extend this to their heating and hot-water systems for their entire site, using a renewable technology with control from within the park and remotely.  Additionally, Hendra had previously endured a poor experience with another installer who had already fitted one biomass boiler – this was not functioning to spec or working in sync with the older supplementary oil boilers.  For the envisaged upgrade we were tasked with fixing the existing install and providing a fully integrated system, requiring minimum supervision and maintenance. The element of control was an essential consideration as it had to be capable of managing and operating the mix of technologies. Given the widespread nature of the park, this presented several challenges distributing the hot water efficiently.

THE SOLUTION

After an extensive technical site survey, IU Energy altered and improved the set-up of the poorly performing boiler and specified an additional low temperature biomass hot water boiler. This was fitted along with an automatic fuel feed from one fuel store, servicing both boilers and minimising attendance and refuelling time. To deliver the hot water across the extensive area required, 200m of new internal pipework was connected through the distribution plant room. An advanced touch screen control system was installed to operate boiler combustion, satellite components and all the peripheral pumps, valves and sensors.

This advanced control technology uses data from across the site to calculate and modulate the required heat demand, thus reducing export temperatures throughout the underground pipeline network and increasing overall system efficiency. The control system’s intuitive user interface is also accessible remotely.

THE RESULTS

The installation was delivered on-time, within budget and immediately performed to spec.

Projected Annual Heating Cost – £10,159
Equivalent Heating Cost from Current Heating Fuel – £19,007
Annual Fuel Cost Saving – £8,848
Total Capital Installation Cost (exc. VAT) – £112,934
Total RHI payment – £379,461
Total Fuel Saving Cost – £176,962
Total Annual Cost Benefit – £27,821
Total Cost Benefit (20 years) – £556,423
System Pay Back (Years) – 4.1

This solution provides a 46% saving over the previous oil-fired boilers that our biomass solution replaced.

You can download this case study here – Hendra Case Study.

CONTACT US

To discuss your own business energy challenges, including commercial electric vehicle charging, talk to us now on 01752 26 26 26 or email info@iuenergy.co.uk.